New Blueberry Fire Hall Construction Update

Work on the new Blueberry Mountain Fire Hall continues, with final site grading to be completed in spring of this year.

Construction work began in late spring 2024, with construction being carried out by K&M Building Contractors (2004) Ltd. As of the end of last year, all interior and exterior concrete work and interior framing is now complete, and exterior and overhead doors have been installed. Electrical and mechanical rough-ins and gypsum boarding is currently underway, with final site grading scheduled for spring 2025.