Work continues on the reservoirs for the Savanna water treatment plant.

F
ormwork and reinforcing installation has begun, sumps base were poured for the pumping and process waste cell chambers and the rest of the sump bases and the pumping chamber base were scheduled to be poured on Tuesday, October 1.